Update: December Building Committee Report

We will be posting occasional updates here about the rebuilding process of Oconee Street UMC here. Last month a Building Committee was established and charged with the massive responsibility of planning and overseeing the rebuilding process.

The Oconee Street UMC Building Committee met Dec. 5, Dec. 17 and Dec. 31. The following information was reported about the rebuilding process:

  • Committee met with contractors to sign off on plans for the interior design of the education building.
  • The committee discussed inventory and creating a mechanism to ensure all new items are accounted for insurance purposes.
  • Committee toured the education building and expressed excitement about the progress being made.
  • Committee received a final insurance estimate for items lost or damaged due to the fire: $38,890.